Change Language:
Equipment Focus
Deadline driven
Volvo paving products help ConnDOT get the job done on time and under budget
Aboeing 747 jumbo jet can weigh more than 800,000 lb at full capacity and has a takeoff speed of 180 miles per hour. Now imagine the full force of 350 aircraft hitting one runway each day. Runway construction specifi cations have to be strictly adhered to, and the contractor has to pave with surgical precision within the allotted time.
So, when Tilcon Connecticut Inc., an asphalt producer and contractor in New England, was given the state contract of repaving Runway 6-24 at Bradley International Airport in Hartford, Conn., they knew they had their work cut out. But with the help of a Volvo PF6110 tracked paver and two Volvo DD138HFA and DD118HF compactors, they rose to the challenge.
“Runway 6-24 is the main runway at Bradley,” said Richard Birge, manager of construction for Tilcon, “But it had to be shut down for three consecutive weekends while we milled and paved. It was imperative that we kept to the schedule.” Bradley Airport is managed by the Connecticut Department of Transportation (ConnDOT) and services more than 6 million passengers annually. The Federal Aviation Administration (FAA) recommends rehabilitation of airport
Think green Astec Inc. has released the second generation of the Double Barrel Green System for producing warm-mix asphalt. The system enables the worldwide network of customers, some of whom are experiencing rising fuel and liquid asphalt prices, to lower their overall operating costs without sacrifi cing quality.
Since its introduction just over two years ago, more than 230 facilities around the world have adopted the use of this system to produce warm-mix asphalt
Runways every 20 years and funded this $17 million project, which entailed not only resurfacing but upgrading the main water line and installing new lighting along the runway.
Like all state highway jobs, if Tilcon missed the completion date, ConnDOT would impose fi nes. So milling and paving crews were scheduled around the clock with up to eight teams working 12-hour shifts.
“There were no rain dates in the schedule,” Birge said. “If it rained a lot, we had to change the hours worked. At times we were operating 24 hours a day.” The FAA stipulated that Tilcon had to mill the 9,500-ft-long, 250-ft-wide runway and apply a 4-in.-thick mat using 62,900 tons of approved hot-mix asphalt.
But because Tilcon’s asphalt plant is 24 miles away from the airport, it had to use a convoy of 30 trucks running back and forth, day and night, to transport 1,800 tons of the material per shift.
The FAA also stated that each paving strip had to be 20 ft wide. But Tilcon decided to pave in 25-ft strips instead, to maximize effi ciency.
The company chose a Volvo PF6110 tracked paver with an Omni 318 screed.
The screed has a standard paving width of 18 ft, so Volvo installed four 1-ft extensions on each side to increase the width.
According to Larry Spring, road paving specialist for Volvo Construction Equipment, the Omni 318 screed provides optimum density, especially at the joints, to achieve the tight specifi cations and traction.
Before paving could begin, the compaction density and quality of the asphalt had to be tried in test strips, which were inspected by ConnDOT and the FAA. Tilcon spent four days becoming familiar with the paver with the help of Volvo’s dealer, Tyler Equipment, which had representatives on hand to provide support and training.
Compaction density requirements also are very stringent for airport paving jobs. Highway contracts usually require 92% compaction density; however, the FAA demands 96.3%. The Volvo DD118HF and DD138HFA double-drum asphalt compactors were selected for the job because they feature eight amplitude settings, allowing the specifi ed amount of force to be applied, preventing overcompaction.
Two DD138HFAs ran behind the paver in an echelon formation for the initial breakdown compaction, then the DD118HF followed for the fi nishing.
“Over-compaction will break down the stone in the mix design,” Spring said.
“If this happens, you lose the stability and strength of the pavement required to handle the airplanes.” ConnDOT performed routine inspections during the compaction, and 5-in.
Core samples were taken for density tests to be performed at its laboratory before the runway could be used.
Runway 6-24 opened on June 23, 2009, and Connecticut Gov. M. Jodi Rell hailed the success of the project, stating it was “on time and under budget.” Tilcon has since repaved Runway 15-33 at Bradley, a smaller project than Runway 6-24. Tilcon has nine paving crews and assumes a majority of state contracts, such as highway road building and repair. It also produces crushed stone and ready-mix concrete.
Volvo paving products help ConnDOT get the job done on time and under budget
Aboeing 747 jumbo jet can weigh more than 800,000 lb at full capacity and has a takeoff speed of 180 miles per hour. Now imagine the full force of 350 aircraft hitting one runway each day. Runway construction specifi cations have to be strictly adhered to, and the contractor has to pave with surgical precision within the allotted time.
So, when Tilcon Connecticut Inc., an asphalt producer and contractor in New England, was given the state contract of repaving Runway 6-24 at Bradley International Airport in Hartford, Conn., they knew they had their work cut out. But with the help of a Volvo PF6110 tracked paver and two Volvo DD138HFA and DD118HF compactors, they rose to the challenge.
“Runway 6-24 is the main runway at Bradley,” said Richard Birge, manager of construction for Tilcon, “But it had to be shut down for three consecutive weekends while we milled and paved. It was imperative that we kept to the schedule.” Bradley Airport is managed by the Connecticut Department of Transportation (ConnDOT) and services more than 6 million passengers annually. The Federal Aviation Administration (FAA) recommends rehabilitation of airport
Think green Astec Inc. has released the second generation of the Double Barrel Green System for producing warm-mix asphalt. The system enables the worldwide network of customers, some of whom are experiencing rising fuel and liquid asphalt prices, to lower their overall operating costs without sacrifi cing quality.
Since its introduction just over two years ago, more than 230 facilities around the world have adopted the use of this system to produce warm-mix asphalt
Runways every 20 years and funded this $17 million project, which entailed not only resurfacing but upgrading the main water line and installing new lighting along the runway.
Like all state highway jobs, if Tilcon missed the completion date, ConnDOT would impose fi nes. So milling and paving crews were scheduled around the clock with up to eight teams working 12-hour shifts.
“There were no rain dates in the schedule,” Birge said. “If it rained a lot, we had to change the hours worked. At times we were operating 24 hours a day.” The FAA stipulated that Tilcon had to mill the 9,500-ft-long, 250-ft-wide runway and apply a 4-in.-thick mat using 62,900 tons of approved hot-mix asphalt.
But because Tilcon’s asphalt plant is 24 miles away from the airport, it had to use a convoy of 30 trucks running back and forth, day and night, to transport 1,800 tons of the material per shift.
The FAA also stated that each paving strip had to be 20 ft wide. But Tilcon decided to pave in 25-ft strips instead, to maximize effi ciency.
The company chose a Volvo PF6110 tracked paver with an Omni 318 screed.
The screed has a standard paving width of 18 ft, so Volvo installed four 1-ft extensions on each side to increase the width.
According to Larry Spring, road paving specialist for Volvo Construction Equipment, the Omni 318 screed provides optimum density, especially at the joints, to achieve the tight specifi cations and traction.
Before paving could begin, the compaction density and quality of the asphalt had to be tried in test strips, which were inspected by ConnDOT and the FAA. Tilcon spent four days becoming familiar with the paver with the help of Volvo’s dealer, Tyler Equipment, which had representatives on hand to provide support and training.
Compaction density requirements also are very stringent for airport paving jobs. Highway contracts usually require 92% compaction density; however, the FAA demands 96.3%. The Volvo DD118HF and DD138HFA double-drum asphalt compactors were selected for the job because they feature eight amplitude settings, allowing the specifi ed amount of force to be applied, preventing overcompaction.
Two DD138HFAs ran behind the paver in an echelon formation for the initial breakdown compaction, then the DD118HF followed for the fi nishing.
“Over-compaction will break down the stone in the mix design,” Spring said.
“If this happens, you lose the stability and strength of the pavement required to handle the airplanes.” ConnDOT performed routine inspections during the compaction, and 5-in.
Core samples were taken for density tests to be performed at its laboratory before the runway could be used.
Runway 6-24 opened on June 23, 2009, and Connecticut Gov. M. Jodi Rell hailed the success of the project, stating it was “on time and under budget.” Tilcon has since repaved Runway 15-33 at Bradley, a smaller project than Runway 6-24. Tilcon has nine paving crews and assumes a majority of state contracts, such as highway road building and repair. It also produces crushed stone and ready-mix concrete.



